  CURRENT STATUS

Progress – Teesta Stage III                                      Week Ending 11.09.2011

Infrastructure Works 100 % of the Works completed
Total Tunneling Area

Completed

(till date In Kms)

Total

(in Kms)

Dam Complex 9.635 9.701
HRT Adits 1.271 1.271
HRT 13.824 13.824
Power House Complex 9.690 9.830
Total 34.420 34.645
Diversion Cum Spillway Tunnel (DT) and Second Spillway Tunnel Coffer Dam Completed. River diverted through DT. Coffer Dam Construction completed.
The excavation of the Second Spillway Tunnel completed except for the plug at the inlet. Till date 1039 m of benching completed from two faces.
Overt lining is in progress from the outlet end. Till date 1113 m of overt lining and 266 m of invert lining completed out of total 1183 m. The excavation of Outlet Channel is completed for the Spillway Tunnel 2.
CFRD and Chute Spillway Materials filling in the 2,2A and & 3A Zones are in progress.
Over 8, 97,857 Cu. m of Material placed in the Dam embankment out of total 12.7 lac.cum (71%). Dam Raised till 1584 level (54 m height in Right bank in 3B and 3C Zones).
Spillway Structure Concreting is in progress in the Surface Spillway.
Cut - off Wall The Excavation of Trench Panels for the Cut off Wall Commenced. Total 61 trenches estimated for the Cut off Wall.
Till date works completed on 24 panels. Works on Two more Panels are under progress.
Power Intake Open excavation

Excavation completed and the Concreting works are underway.
The laying of Concrete Slab is in progress. Reinforcement works is in progress in the Flushing Tunnel Intake Portal.

172 m of overt lining Intake Tunnel completed out of total 420 m

Right Bank Tunnels Excavation is in progress in the Hopper & Flushing Conduit Portion in both the Desilting Basins.
The Excavation of Silt Flushing Tunnels completed. Concreting to be taken up soon.
The Excavation of Inspection Galleries completed.
The Excavation of Gate Chamber and Gate Shafts is in progress in the Desilting Basins and the Silt Flushing Tunnels.
The Excavation of Flushing Tunnel completed and Till date 1082 m of Overt lining completed.
The Outlet Channel excavation for the Flushing Tunnel completed and  reinforcement & concreting is in progress
.
Head race Tunnel HRT Excavation completed. 5,856 m of Overt lining of HRT completed and 547 m of Invert Lining of HRT Completed.
Contact grouting commenced in the HRT. Till date cumulative of 1198 m completed out of total 13824 m
Surge Shaft A total of 81.5 m pilot hole and 76.5 m of Full Face sinking completed in the Surge Shaft.
Breakthrough achieved between the Pilot Face and the Sinking Face.
Slashing of the Pilot Hole commenced. Till date 33 m Slashing Completed.
Pressure Shafts Excavation of VPS 1 completed.
Breakthrough achieved in VPS2 between Pilot Hole and Sinking Face.
Slashing works commenced in VPS2. Till date 161 m completed out of 255 m.
The Excavation of the Inclined Shaft 1 and 2 completed. The excavation of all the penstocks completed.
Erection of Ferrules -  Pressure Shafts

Penstock No.1 – Fifteen No’s of Ferrules Erection completed out of 18.
Penstock No.2 - Nine No's of Ferrules Erection completed out of 10.
Penstock No.3 - Six No's of Ferrules Erection completed out of 7.
Penstock No.4 - Eighteen No’s of Ferrules Erection completed out of 19.
Penstock No.5 - Nine No’s of Ferrules Erection completed out of 10.
Penstock No.6 - Six No’s of Ferrules Erection completed out of 8.
Top Horizontal Pressure Shaft. - Four No's of Ferrule  Erection completed  out of 23.
Vertical Pressure Shaft  - 1 no of Ferrule errection completed out of 436.
Inclined Pressure Shaft  - 2 no of Ferrule errection completed out of 308

Power House Civil Works Power House Excavation completed.
The excavation TRT Completed. Invert Concreting in Progress. Concreting Lining works started.
Transformer Hall cavern Excavation completed.
GIS   cavern Excavation completed.
All Units handed over to the E&M Contractor after the completion of necessary Civil works.
Unit No.1, 2, 3, 5 & 6 second stage concreting completed. 3rd Stage concreting Progress in Unit No 1 & 5.
Control Room Slab Reinforcement works are under progress.
Transformer Cavern Reinforcement works commenced in Transformer hall.
E&M Works

Vertical Pelton Turbine: Three nos. of pelton turbine (For unit 1, 2&3) have been inspected by TUL.
Main Inlet Valve (MIV) : Six (6) nos. casting of MIV body & Rotor (For all 6 unit ) have been inspected and final machining is under progress. Nozzles and Distributors: Five (5) nos. of nozzles and 4 No's of Distributors have been inspected.
Turbine Housing and Generator Shafts: Five (5) nos. of Turbine Housing (For unit 1 to 5) and One (1) no. Turbine shaft (for unit 1) has been inspected.
Distributors: 4 Nos. Distributors reached the Storage Yard in Siliguri. Being under transportation to the site.
Bus Duct: Bus Duct for four (4) units have been inspected and ready for machining.
Unit-5 stator frame reached at Storage yard in site.
EOT crane -1 Main hoist hook and Auxiliary hoist hook with rope erection completed. EOT Load Test in progress.
Unit No.1: Turbine Housing erection (Lower & Upper) works are completed & Distributor Pipe Erection and its support works completed. Distributor Hydro Pressure test successfully completed. Generator Support work under progress. Distributor pipe Erection & its support works completed. Pressure Test had successfully completed.
Unit No.2: Turbine Housing Erection completed. Distributor Pipe & its supports work erection under progress.
Unit No.3: Turbine Housing Erection completed. Joint welding works under progress.
Distributor Pipe placed in position.
Unit No.4: Unit platform errection in progress.

Unit No.5: Turbine Housing erection (Lower & Upper) works completed. Stator assembly & Generator Support work under progress. Distributor pipe Erection & its support works completed. Distributor Hydro test under Progress.
Unit No.6 Turbine Housing erection (Lower & Upper)is in completed. Stator assembly & Generator Support work under progress. Distributor pipe Erection & its support works completed. Pressure Test had successfully completed.
Generator barrel work and roter assembly works under progress.